The use of POD construction on site has the potential to reduce on site wastage rates.
Off site Solutions has been identified as an exemplar to demonstrate the manufacturing process that has been developed to reduce production wastage.
Key facts:
- The use of POD off site construction has the potential to reduce on site construction wastage by 50% compared to traditional build.
- The production process has a wastage rate of 1% at the factory and 0% on site.