Commercial Refurbishment, London

Date
2006
Documents
Download pdf
(78 kb)

A review of the fit out stage of a £30 million Morgan Stanley office refurbishment in London showed very high levels of waste recovery with 100% of plasterboard and 95% of metals, timber and packaging being recovered.

Identification and implementation of Waste Recovery Quick Wins would result in an increase of 11% in the overall project recovery performance.

Key facts:

  • Even with some material streams achieving 100% recovery there is still potential to improve the overall recovery performance by focusing on specific materials.
  • The Quick Win materials for this project were identified as metals and miscellaneous wastes.